Practice Test: Question Set - 03
1. Critical path method
- (A) Helps
in ascertaining time schedules
- (B) Makes
better and detailed planning possible
- (C) Provides
a standard method for communicating project plans schedules and to time and
cost performance
- (D) All
of the above
2. Critical Path Net Work helps an engineer
- (A) To concentrate his
attention on critical activities
- (B) To divert the
resources from noncritical advanced activities to critical activities
- (C) To be cautious for
avoiding any delay in the critical activities to avoid delay of the whole
project
- (D) All of the above
3. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
- (A) One-fourth
- (B) One-half
- (C) Equal
to
- (D) Twice
4. In break-even analysis, total cost consists of
- (A) Fixed cost
- (B) Variable cost
- (C) Fixed cost + variable
cost
- (D) Fixed cost + variable
cost + overheads
5. Which one of the following techniques is used for determining allowances in time study?
- (A) Acceptance
sampling
- (B) Linear
regression
- (C) Performance
rating
- (D) Work
sampling
6. Expediting function consists in keeping a watch on
- (A) Operator's activity
- (B) Flow of material and
in case of trouble locate source of trouble
- (C) Minimizing the delays
- (D) Making efficient dispatching
7. The most popular type of organisation used for Civil Engineering Constructions is
- (A) Line organization
- (B) Line and staff
organization
- (C) Functional
organization
- (D) Effective
organization
8. Which one of the following chart gives simultaneously information about the progress of work and machine loading?
- (A) Process
chart
- (B) Machine
load chart
- (C) Man-machine
chart
- (D) Gantt
chart
9. Merit Rating is the method of determining worth of
- (A) A job
- (B) An individual employee
- (C) A particular division
in workshop
- (D) Machine
10. Routing is essential in the following type of industry
- (A) Assembly industry
- (B) Process industry
- (C) Job order industry
- (D) Mass production
industry
11. The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as
- (A) Rowan Plan
- (B) Taylor Differential
Piece rate system
- (C) Halsey Premium plan
- (D) Day work plan
12. Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?
- (A) Halsey plan
- (B) Gantt
plan
- (C) Rowan plan
- (D) Emerson's
efficiency plan
13. Bin card is used in
- (A) Administrative wing
- (B) Workshop
- (C) Foundry shop
- (D) Stores
14. The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
- (A) Product
layout
- (B) Process
layout
- (C) Fixed
position layout
- (D) A combination
of line and process layout
15. The disadvantage of product layout is
- (A) High initial
investment for the specialized facilities
- (B) Skilled labour to operate machines
- (C) Production time is
longer, requiring more goods in inventory
- (D) High cost of
inspection