Practice Test: Question Set - 03
1. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
- (A) 2.3% and 84.1%
- (B) 97.7% and 84.1%
- (C) 97.7 % and 15.9%
- (D) 15.9% and 97.7%
2. Power stations are generally treated as
- (A) Light
construction
- (B) Heavy
construction
- (C) Industrial
construction
- (D) Electrical
construction
3. For a given size of bucket, the ideal output of a dragline will be least in
- (A) Moist loam
- (B) Sand and gravel
- (C) Good common earth
- (D) Wet sticky clay
4. Bar charts are suitable for
- (A) Minor works
- (B) Major works
- (C) Large
projects
- (D) All the
Above
5. The time corresponding to minimum total project cost is
- (A) Crash time
- (B) Normal time
- (C) Optimistic time
- (D) Between normal time and crash time
6. Construction team means
- (A) An engineer
- (B) An architect
- (C) An owner
- (D) All the
above
7. Select the incorrect statement.
- (A) Start float and finish float are always equal
- (B) Total float can be either start float or finish
float
- (C) Start float and finish float need not be equal
- (D) Start float and finish float are the differences
between activity times and not event times
8. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
- (A) Event
- (B) Free float
- (C) Dummy
- (D) Constraint
9. PERT technique of network analysis is mainly useful for
- (A) Small projects
- (B) Large and complex projects
- (C) Research and development projects
- (D) Deterministic activities
10. Pick up the correct statement from the following:
- (A) The
float may be positive, zero or negative
- (B) If the float
is positive and the activity is delayed by a period equal to its total float,
the completion of project is not delayed
- (C) If
the float of an activity is negative, delay in its performance is bound to
delay the completion of project
- (D) All the
above
11. The independent float affects only
- (A) Preceding activities
- (B) Succeeding activities
- (C) The particular activity involved
- (D) None of the above
12. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
- (A) Duration
- (B) Total float
- (C) Free float
- (D) Interfering
float
13. The part of a derrick crane include
(i) Mast
(ii) Boom
(iii) Bull wheel
(iv) Jack
Of these statements
- (A) (i), (ii) and (iv) are correct
- (B) (ii), (iii) and (iv) are correct
- (C) (i), (iii) and (iv) are correct
- (D) (i), (ii) and (iii) are correct
14. Site order book is used for recording
- (A) Instructions
by the executive engineers
- (B) Construction
measurements
- (C) Issue
of store equipments
- (D) Names of the
casual labour
15. If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
- (A) 30 kg
- (B) 300 kg
- (C) 900 kg
- (D) 1000 kg