Practice Test: Question Set - 02
1. Pick up the correct statement from the following:
- (A) The earth
work of cutting in trenches or borrow pits in fairly uniform ground is measured
with the help of average depths of the dead men
- (B) The earth
work in trenches or borrow pits in irregular ground is measured by taking the
difference in levels before and after completion of work
- (C) The earth
work in trenches or borrow pits, where neither a nor b is feasible, are
measured from the fillings after deduction of voids
- (D) All the above
2. The cross-sections for a highway is taken at
- (A) Right angle
to the centre line
- (B) 30
meters apart
- (C) Intermediate
points having abrupt change in gradient
- (D) All
the above
3. Referring of given figure, pick up the correct statement from the following:
- (A) The total
length of centre line of four walls is 20 m
- (B) Length of
long wall out-to-out is 6.80 m
- (C) Length of
short walls in-to-in is 3.20 m
- (D) All the
above
4. Pick up the correct statement regarding the centre line method of estimating a building
- (A) Product
of the centre line of the walls and area of cross-section of any item, gives
total quantity of the item
- (B) The centre
line is worked out separately for different sections of walls of a building
- (C) The
centre line length is reduced by half the layer of main wall joining the
partition wall
- (D) All the
above
5. According to Indian Standards Institute, the actual size of modular bricks is
- (A) 23 cm × 11.5
cm × 7.5 cm
- (B) 25 cm × 13
cm × 7.5 cm
- (C) 19 cm × 9 cm
× 9 cm
- (D) 20 cm × 10
cm × 10 cm
6. The following item of earth work is not measured separately.
- (A) Setting out
of works
- (B) Site
clearance
- (C) Steps
in deep excavation
- (D) All
the above
7. The measurement is made in square metre in case of
- (A) Cement
concrete in foundation
- (B) R.C.C.
structure
- (C) Hollow
concrete block wall
- (D) None of
these
8. The area of the cross-section of a road fully in banking shown in the given figure, is
- (A) [sb² + r² (2bd + sd)²]/(r² - s²)
- (B) [sb² + r² (2bd + sd)²]/(r² - s5)
- (C) [sb² + r² (2bd + sd)²]/(r - s)
- (D) None of
these
9. Cost of fittings and their fixing is specified for the following sanitary fittings
- (A) Water
closets
- (B) Flushing
pipes
- (C) Lavatory
basins
- (D) All
the above
10. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as
- (A) Excavation
- (B) Surface
dressing
- (C) Cutting
- (D) Surface
excavation
Blogger Comment
Facebook Comment